POWER LINE WARNING
Panaji : September 09, 2025
The newly laid 11KV 3C x 300 sqmm cable at 11 KV Industry I feeder, II feeder and III feeder to 11KV underground system along the road from 33/11 KV Kundai Substation to the areas of Kundai Industrial Estate under the jurisdiction of SD III ®, Div X Curti, Ponda and also the newly erected 1 no. of 100 KVA Distribution transformer center at Plot no. B25-26/08, Kundai Industrial Estate, Kundaim has been test charged on September 4, 2025 and will remain charged thereafter.
All the general public are therefore requested to keep away from the installation and associated lines directly or indirectly as it is dangerous to the life of human beings and animals.
DI/INF/AXP/SAG/SS/SN/2025/687